Project summary

Location: London
Sector: Office
Client: General Projects
Architect: Feix & Merlin Architects
Consultant: Red Engineering
Electrical Contractor: MJ Electrical
Main Contractor: Conamar
Value: £450k
Duration: 12 months
Size:  192,600 sq. ft
Photography: Tian Khee Siong

At a glance: Walworth Town Hall, London is an office project for General Projects. 299 Lighting provided the lighting, working with Feix & Merlin Architects (architect), MJ Electrical (electrical contractor) and Red Engineering (consultant). The overall redevelopment covers approximately 50,000 sq ft.

The recently completed £21m refurbishment project  of one of London’s most iconic civic buildings, Walworth Town Hall is a testimony to the client's commitment to bring a derelict building back to its former glory. Celebrating its rich heritage and  preserving the architectural details, the 50,000 sq ft building is going to serve the local community as a mix of workshops, studios and public event spaces. The adjacent building, formerly the Newington Library, will house the new community centre, as well as more workspaces.

Designed by Peckham-based Feix & Merlin Architects  and brought to life by Conamar, the iconic 2 storey building is another jewel in General Projects' property portfolio.

 


Originally built between 1865 and 1906, the Grade II listed Victorian building was latterly home to the Newington Library and Cuming Museum until it was badly damaged by fire in 2013. It was then placed on the Heritage at Risk Register and closed. Now, after sensitive restoration by Feix & Merlin and General Projects, it reopens its doors again, celebrating its former glory while embracing its future.

 

Walworth Town Hall

45 Hours of Lighting Design

Following the architect’s vision and aiming to achieve the CIBSE recommended illumination levels, we proposed new linear LED lighting as the general lighting for the entire historic building. Our technical team put forward the popular 60 mm linear profile Rio Suspended direct. Achieving all current light guidelines, providing good quality light distribution, and achieving clean, contemporary aesthetics was the key for this project.

Over 45 hours of lighting design, including emergency lighting design, were allocated to secure and support this project.

highres-DSC_3025

The design brief

The design brief for the Walworth Town Hall was driven by the careful restoration and preservation of architectural details, whilst creating a dynamic cultural community hub. All lighting had to work with the historic nature of the building and work around the existing fabric of the building.

 


highres-DSC_2999

What was the most interesting aspect of the project?

“Due to the nature of the building, there is no DALI system in the building and that means, all fittings had to be supplied as non-dimmable. In order to achieve high level of visual comfort, we fixed the output of certain light fittings to help reduce the light output."

Track Lighting

The new central atrium has become the active soul of the building. A completely new mezzanine level was inserted into the former council chamber. This created a completely new and unique workspace. 

The mezzanine was lit by track lighting, which supplements the decorative wall lighting fixtures. Fully adjustable, the architectural track lighting Venta is a popular choice for small, minimalist and versatile track lighting. The LED tape installed into the joinery detail of the ceiling adds another layer of light into the space, making it feel more soft, homely and comfortable.

trendy co working space with nice lighting

Office Lighting

Aesthetically, the open plan office areas and studios are the same, all using suspended linear lighting as the general lighting. The designer's favourite Rio Suspended was used throughout the entire scheme as the main office lighting. The suspended lighting has been supplied in two standard lengths, 1200 and 1800 mm. All linear lighting is fitted with a microprismatic diffuser. As there is no Dali system in the building, due to the historical nature of the building, the fittings have been all supplied as non-dimmable. Following the lighting design and exact requirements for the building, some linears were factory adjusted to certain outputs.

In the circulation areas, we used the can style fitting Sett Suspended and Sett Surface mounted. The Sett offers a contemporary alternative to downlights and looks great in any commercial setting.

highres-DSC_3013

The scheme uses the combination of 4000K and 3000K colour temperatures and high CRI throughout. All suspended LED linear lighting was supplied in a contemporary matte black finish with 4000K. All fittings are non-dimmable.

All types of emergency lighting were also supplied following closely the emergency lighting design schedule. This included integrated emergency lighting for the main office space and back of the house areas, emergency exit signs and emergency bulkheads.highres-DSC_3098

 

The final result is a forward thinking and contemporary CAT B scheme designed to enhance the original fabric of the building. It is looking fantastic and we are very proud to have been part of this redevelopment. 


Project in figures:

45 Hours of Lighting Design

15 Revisions

45 Sett Suspended fittings

Working on a unique or listed building project and need assistance?

Our team has the experience and expertise to help you every step of the way. Talk to us to see how we can help.

Working on a unique or listed building project and need assistance?

Our team has the experience and expertise to help you every step of the way. Talk to us to see how we can help.

Planning something similar?

Send us your drawings or schedule and we will reply within one working day. Layouts and calculations are included when we supply the fittings.

  • Architects & interior designers: samples, finishes and made-to-measure options
  • Contractors: fast quotes, lead times and delivery to programme
  • M&E consultants: photometrics, BIM, LDT files and calculations

Send us your drawings

We reply within one working day with fittings, layouts and calculations, and a quote you can price against.

Request a quote

Or call London 020 3773 7530 or Bristol 0117 942 2512